Construction Progress

34 mile Conveyance System Pipelines    LEARN MORE
Segment 1    VIEW MAP
The first piece of pipe was installed for segment 3 of the conveyance system near Jewell Avenue.
100 percent complete

Final Completion was achieved June 1, 2010.

Segment 2    VIEW MAP
100 percent complete
   
Segment 3    VIEW MAP
97 percent complete
All of the pressure testing on the Prairie Waters Raw Water line has been completed.

All seeding and fencing has been completed.